Challenge
To fit all the structural elements into a complex perimeter concrete substructure. Creation of a temporary structure for mounting 75m lattice girders.
Success factor
Reliability of software, collision detection, rapid creation of assembly sheets, use of macros.
BIM benefits: No need to rework the model, thanks to import of elements from other batches (electrical, HVAC, concrete, etc.). Allows full verification of the model by the design engineer, ensuring safe construction.
Proudest feature: Modeling of 210 truss nodes and 36 member splices, for 75m truss beams.