This is a 1400 seat performing arts center at Alta high School in Sandy Utah.  This project is a mix of tilt panels and structural steel. The project was started in 2018 and will be completed on schedule in early 2020. Â
The main challenge with this project was verifying the tilt panels were installed accurately to allow the connecting the structural steel. Â This project also contained very large duct work that we needed to coordinate with for some of the access ladders and stairs. Â Early coordination of the tilt panels, concrete and MEP made for a successful project.