Architectural feature stair and atrium balustrade for investment banker offices accessing 4 floors. We commenced drawing work in August 2017.Â
Issued fabrication details of a mock up stair for client inspection and approval September and followed up with the complete stair fabrication package in November. Stairs were delivered to site in February and installation commenced of the main structure was completed in less than one week in March. Stairs will have temporary treads and all glazing cladded until final fit out May 2019.