BHC successfully completed the construction of a new GIS Control Building and two SGT Buildings near Peterhead Substation. This project posed significant coordination challenges, requiring a wide range of expertise.
Â
Challenges
Coordinating multiple elements, from structural components to cladding, presented a major challenge. Tekla Structures played a crucial role in integrating various elements into a single model, ensuring accurate ordering and eliminating human errors. Additionally, Tekla's capabilities facilitated clash detection, enabling efficient crane placement and site scheduling, even in adverse weather conditions.
Â
Achievements
- BHC's use of Tekla's API ensured efficient modelling for CNC machines and fabrication processes.
- By automating tasks such as checking hole placement and adding customised details, errors were minimised, allowing for accurate and timely delivery.
- The integration of crane and equipment models facilitated clash detection and enabled precise site planning.